1. COMPLETED

No Project Name Type of IT Service Status % Remark Quarter
1 2 3 4

 1.

INF Microsoft 365 Migration Phase 4

Objective : To improve licensing management
Investment : RM 27,500

Business: Swine

Type of IT Services: Application Integration, Implementation, and Support


Priority: Med


CPF IT TH:


3 Mar 23
-
Success migration to Office365
23 Feb 23
-
 Setup  AD Sync and assign license to user completed
- Onsite Training for Office365 will be schedule on 27 Feb - 7 Mac
- AD CP-MJGROUP already setup
- User created in AD
- Multiple domain already config in Firewall and Clearpass and user will connect with ssid CP-MJGROUP@Staff 
12 Jan 23
Waiting GoSoft revise quotation
    1) E1 reduce from 120 to 70
    2) E3 reduce from 25 to 20
- AD server will setup after CNY

       
 2.

APP SMARTSoft_Food - Plan 8 Weeks
Plan 8 weeks 

Objective : To implement a planner for 5 weeks for winfood

Investment : USD 7,283.00

Business: Agro - Food

Type of IT Services: Application Integration, Implementation, and Support

Priority:

CPF IT TH:

  29 Mar 23
- User already signed forms and done upload in itso.project
17 Mar 23
- Preparing all form for distribute to users sign
08 Feb 23
- Already done meeting on 8/2/2023, on the user side they already confirm the progress already run smoothly and already go live . Agro side already complete implementation project.
       
3.

INF Network Connectivity Upgrade SDWAN for IP Value & IP Lite
Objective :
 To expand business
Investment : 

Business: All
Type of IT Services: 
Application Integration, Implementation, and Support
Priority: 
Med
CPF IT TH:

13 Apr 23
- Complete SDWAN installation for AVM-Kota Hatchery on 11 Apr 2023 
17 Mar 23
Complete SDWAN installation for AVM-Tampin on 15 Mar 2023 
15 Feb 23
Complete SDWAN installation for CYF-Siputeh on 19 Jan 2023

12 Jan 23
 Target site for installation SDWAN

    1. CYF-Siputeh Farm - on CNY week (22-23 Jan 23)

       

2. ONGOING

2.1 SELF IMPLEMENTATION

No Project Name Type of IT Service Status % Remark Quarter
1 2 3 4
1.

INF Manage Engine EndPoint Central
Objective :
 To reduce the workload and empower IT Teams to troubleshoot rapidly, improve productivity and security and reduce cost
Investment : Annual Subscription RM130 per computer

Business: All

Type of IT Services:

Priority: Med

CPF IT TH:

15 May 23
-
Total Installation agents 689
13 April 23
-Continue UAT session on 12 Apr 2023 to complete pending task
17 Mar 23
-
 Arrange for UAT session on 21 Mar 2023
15 Feb 23

-  Success setup Endpoint Central in server
-  Discover computer and server completed
-  In progress push agent and deploy software (Sophos)

12 Jan 23
-  Arrange Kick-Off Meeting with vendor on Jan 18 | Wed

       
2. INF Security Hardening
Objective : To reducing a system's vulnerability
Investment : RM 10,000

Business: ALL

Type of IT Services: Infra Service Delivery

Priority : Med

CPF IT TH:

 

15 May 23
-
Currently using Cyberark for Domain Admin and Server Admin account
13 Apr 23
-
For previous error in cyberark already clarify with TH admin and current still on testing Domain Admin and Server Admin for login all server

29 Mar 23
-
Already test the account added but got error.
- Planning arrange session on 30/3/2023 with CyberArk TH Admin 
15 Feb 23
-  
Already provide Enterprise admin, Domain admin and Server admin to TH add in CyberArk
12 Jan 23

-  Session with TH team on 12/1/23 to discuss about adding the Enterprise admin, Domain admin and Server admin.
09 Nov 22
- Arrange session with TH team on 11/11/22 for Cyberark to discuss MY team to be a Cyberark admin
12 Oct 22
- Installation Crowdstrike will continue for new computer deployment

- CyberArk will start pilot add domain admin or server admin
19 Sep 22
Still ongoing installation Crowdstrike for existing & new computer 

       
3.

INF Tech Refresh Computer
152 computers
Objective : To replace old computers with aged more than 5 years due to end of life, end of support and no spare part replacement available
Investment : RM 613,600

Business: All

Type of IT Services:

Priority: Med

CPF IT TH:

26 May 23

- Desktop = 17
- Laptop = 13
- Total = 30

18 Apr 23

- Desktop = 7
- Laptop = 7
- Total = 14

29 Mac 23

- Desktop = 3
- Laptop = 0
- Total = 3

11 Jan 23

- Received IO from Aqua Business

10 Jan 23

-  Waiting for IO number to release 
Desktop = 122
Laptop = 30

       
4.

INF Tech Refresh Network Switches 2022 - P1 (2 Sites)
SFM Beranang Feedmill & AA - Desaru Hatchery
Objective : To refresh old switch with Cisco C9300 and Cisco C9200
Investment : SFM-Beranang (RM169 000.00) & AA-Desaru Hatchery (RM121 000.00)

Business: Aqua

Type of IT Services: Application Integration, Implementation, and Support
Priority: Med
CPF IT TH:

 

15 May 23
- Installation for SFM Beranang on 8 & 11 June 23
14 Apr 23
- Target installation for 
  1. SFM-Beranang on 24 - 26 May 2023
  2. AA-Desaru on 29 - 30 May 2023
17 Feb 23
- The switches by latest will be deliver on May 2023
11 Jan 23
-
ETA on Q3
19 May 22
PO already issue to vendor

- Estimate 30weeks to deliver the goods by vendor
07 Apr 22
- 4 vendors submitted pre quotation

- Tender presentation on 13 April 2022 
23 Mar 22
- Tender Briefing Presentation

       
5.

INF Tech Refresh Network Switches 2022 - P2 (8 Sites)
Cisco C1000 : Aqua ( 3 Sites) and Agro (5 Sites)
Objective : To refresh old switch with Cisco C1000
Investment : Aqua (RM21 000.00) & Agro (RM35 000.00)

Business: ALL

Type of IT Services: Application Integration, Implementation, and Support

Priority: Med

CPF IT TH:

15 May 23
-Pilot site installation for AVM-Kota Breeder on 25 May 23
14 Apr 23
- Target installation for P2 on 29 May - 1 June 2023
17 Feb 23
The switches by latest will be deliver on May 2023
12 Jan 23

-ETA on Q3
19 May 22
PO already issue to vendor

Estimate 30weeks to deliver the goods by vendor
07 Apr 22
- 4 vendors submitted pre quotation

- Tender presentation on 13 April 2022 
23 Mar 22
- Tender Briefing Presentation
       
6.  

INF & APP Migrate All Windows Servers 2008

- SMARTSoft (3)
- SmartSoft_Feed (2)
- SMARTSoft_Farm(3)
- SMARTSoft_Food (2)
Objective : To migrate OS Windows Server 2008 to OS Windows 2012/2016
Investment : N/A

Business: ALL

Type of IT Services: Infra Service Delivery

Priority : High

CPF IT TH:

     

13 Feb 23
-Swine-farm success Golive in 13 Feb 2023
-Aqua-farm success Golive in 14 Feb 2023
12 Jan 23

Phase 2
-
Start on Q2
12 Dec 2022
Phase 1

- SMARTSoft AquaFeed success Golive in 12 December 22
09 Nov  22
Phase 1
- TTM-WFOOD success Golive in 17 October 22

- SMARTSoft Agro Feed success Golive in 25 October 22
Phase 2
-SMARTSoft  Farm Agro, Aqua, Swine Golive in Nov 22
13 Oct 22
Phase 1
- TTM-WFOOD Golive in 17 October 22

- SMARTSoft Agro Feed Golive in 25 October 22
Phase 2
-SMARTSoft  Farm Agro, Aqua, Swine Golive in Nov 22
19 Sep 22
- PKA-WFOOD Golive in 12 Sep 22
8 Aug 22
3 Servers Smartsoft success GoLive

- 2 Servers SmartSoft_Food will GoLive in mid September
4 Aug 22
All Windows Server 2008 completed migrate
19 Jul 22
Completed migrate SmartSoft_Feed Agro & Aqua

23 May 22
- Windows 2008: 3/10

- SS Agro, SS Swine & SS Aqua

       
7.

INF Tech Refresh Network Switches 2023 - P2 (4 Site)
Cisco C1000 : Aqua ( 2 Sites) and Agro (2 Sites)
Objective : To refresh old switch with Cisco C1000
Investment : Aqua (RM14 000.00) & Agro (RM14 000.00)

Business: ALL

Type of IT Services: Application Integration, Implementation, and Support

Priority: Med

CPF IT TH:

  22 May 23
-
Waiting user open PR
14 Apr23
-
Waiting quotation from vendor
17 Feb 23
-
Arrange tender presentation on March
       

 

2.2 CPF IT IMPLEMENTATION

2.2.1 WAITING FOR CPF IT

2.2.1.1 ALL

No Project Name Type of IT Service Status % Remark Quarter
1 2 3 4

1.

APP Order to Cash (OTC)
Account Receivable System Enhancement

Objective : Set criteria/ The process that should be adapted to Business type and customers
Investment : NA

Business: ALL

Type of IT Services: Application Integration, Implementation, and Support

Priority:

CPF IT TH: 

26 May 23
-
Waiting for clone data from prd to uat about 4.8 framework
12 May 23
-Finished setup master and config
18 Apr 23
-
Ms Frame currently test and alter the table


       
 2.

APP ILogistic
Feed / Farm / Food

Objective : Route management application for business
Investment : RM150000.00 (Senawang)

IO No. : xxxx (RM xxxx) 

Business: ALL

Type of IT Services: CPF IT - TH

Priority: High

CPF IT TH: On Site

  (CC2020148263) - 2020

26 May  23
- Already sent follow up email to TH for follow up. Still on testing phase 2
13 Apr 23
-
Waiting for update from TH side for phase 2 testing
23 Feb 23
- For Agro site already Start on Phase 2
- TH side is testing for phase 2

       
3. 
Plan Replace SAPPO - Interface API04

Objective : To replace SAPPO - Interface API04


Business: 
ALL

Type of IT Services: CPF IT - TH

Priority: High

CPF IT TH: 

  26 May 23
- Already go live on 1st May
13 Apr 23
-
All completed for PRD, will monitor for one month
17 Mar 23
-
txt file succesfully interface to SAP.
- A total of 5 files were entered and the files were moved to the PO-510 Archive folder.
       
4. 

APP SMARTSoft_iWorkflow
Approve Credit Control for all BU

Objective :
Investment : 


Business:
 ALL

Type of IT Services: Application Integration, Implementation, and Support

Priority:

CPF IT TH: 

  Ser No. : 36044 (CC2019085571) - 2019

07 May 22
- Waiting plan from PMO

24 Jan 22
- Waiting plan from Mr Sampan and SSC team from TH

24 Mar 21
- Implement after SMARTHR

       

5.

APP New SMARTHR
Time off (Online Leave Application)

Objective : 
Investment : RM70000.00 (All sites)


Business:
 ALL

Type of IT Services: CPF IT - TH

Priority: High

CPF IT TH: On Site

 
(CC2020109657) - 2019

24 Jan 22
- Will start at Q4 
25 Jan 21
HRIS TH meeting with Agro HR on 27 Jan 21
06 Dec 20
- IT TH prepare Cloud AWS
       

6.

SAP Key Sucess Factor

Time off (Online Leave Application)

Objective : 
Investment :  (All sites)


Business:
 ALL

Type of IT Services: CPF IT - TH

Priority: High

CPF IT TH: On Site


24 Jan 22
- Will start at Q4 
       

 



2.2.1.2 FEED BUSINESS

No Project Name Type of IT Service Status % Remark Quarter
1 2 3 4
1. 

APP SMARTSoft_Feed PDA system for RM

Objective : To improve the efficiency of intake dumping system and to prevent the error while intake delivery process

Investment :
PKF : RM25,123 (PDA 3 units) + RM25000 (AP 3 units with internal wiring)
BWF : RM 25,123
TLF : RM25,123 
SFM : RM25,123 

Total : 125,492

Business: Aqua & Agro Feed

Type of IT Services: Application Integration, Implementation, and Support

Priority: Med

CPF IT TH: On Site

 

Ser No. : 40055 (CC2020032984) - 2020

26 May 23
Planning go live on Jun
12 May 23
All issue fixed. Will test all the function again before prepare to go live
13 Apr 23
- Adjust and test crystal report format for pallet sticker
17 Mac 23
- TH still checking for case Move lock, transfer, intake change to WAIT product code after scan and save PDA
- Ask TH to adjust crystal report format for pellet sticker

       
2. 

POWERBI Feed Sales

Objective : To view and record feed sales in dashboard

Investment : NA

Business: Aqua & Agro Feed

Type of IT Services: Application Integration, Implementation, and Support

Priority: Med

CPF IT TH: On Site

  26 May 23
- Waiting BI team to give access to user
12 May 23
- Uploaded Target Master data to DB.
- BI team request to list the long lat for MY state to include in Dashboard
14 Apr 23
-
Email user list to BI team to request access
       
3.

[Upgrade AQUA] SMARTiQC - Raw material Receiving Inspection

Objective : Upgrade SMARTiQC system to new version and change RFID device to new device since the old system not compatible with new RFID 

Investment : 

Business: Aqua Feed

Type of IT Services: Application Integration, Implementation, and Support

Priority: Med

CPF IT TH: On Site

  26 May 23
- Appear strange column in table, effect other module. Waiting to solve all the issue.
02 May 23
- After test at PRD, still got error 'table/view not found', re compare the db and test again.
14 Apr 23
- Testing at UAT server, found one error waiting for TH to respond
       
4.

APP SMARTSoft_Feed _Batching_System

Interface batching system auto issue usage

Objective : To automatically interface data of Production Batching Report and Balance Stock Bin report to SMARTSoft_Feed

Investment : 

Business: Agro - Feed

Type of IT Services: Application Integration, Implementation, and Support

Priority: 

CPF IT TH:

 

26 May 23
- User testing,waiting data from warehouse (stock in BIN, user need to move stock location) 
12 May 23
- Meeting with Feed team to review again whole process on 10 May
- batching data successfully interface to winfeed 
14 Apr 23
Waiting for all side available to discuss for the next step

       
 5. SmartiQC - Inprocess Inspection

Objective : Convert questionaire/checklist paper to system.

Investment :

Business: Agro Feed

Type of IT Services: Application Integration, Implementation, and Support

Priority: Med

CPF IT TH:

  29 Mar 23
-
Start to implement on Aug
17 Mar 23
-
Project overview and introduction with QC TH and QC local on 21 Mar
03 Mar 23
-
Waiting QC TH to explain project overview and train QC Local and IT. Date TBC
       
6.

RM & Feed Storage Inspection V.2022

Objective : QC check physical sample at Warehouse

Investment :

 

Business: Agro Feed

Type of IT Services: Application Integration, Implementation, and Support

Priority: Med

CPF IT TH:

  29 Mar 23
Start to implement on Aug
17 Mar 23
Project overview and introduction with QC TH and QC local on 21 Mar
03 Mar 23
-
 Waiting QC TH to explain project overview and train QC Local and IT. Date TBC
       
7.  Production Sequence V.2017

Objective : To send email notification to check production before produce new feed

Investment :

Business: Agro Feed

Type of IT Services: Application Integration, Implementation, and Support

Priority: Med

CPF IT TH:

  29 Mar 23
-
 Start to implement on Aug
17 Mar 23
Project overview and introduction with QC TH and QC local on 21 Mar
03 Mar 23
- Waiting QC TH to explain project overview and train QC Local and IT. Date TBC
       
8.  Quality and Stock Information System

Objective : 

Investment :

Business: Agro Feed

Type of IT Services: Application Integration, Implementation, and Support

Priority: Med

CPF IT TH:

 

29 Mar 23
Start to implement on Aug
17 Mar 23
-
 Project overview and introduction with QC TH and QC local on 21 Mar
03 Mar 23
Waiting QC TH to explain project overview and train QC Local and IT. Date TBC

       

9.

APP SMARTOrder
Order Online

Objective : Sales Order Approval and Credit Checking

Investment : 

Business: Agro - Feed

Type of IT Services: CPF IT - TH

Priority: 

CPF IT TH:

 

Ser No. : 36044 (CC2020095257) - 2019

23 Feb 22
- Waiting TH Side
24 Jan 22
- Will start at Q3

16 Nov 21
- Demo iFarm Sale and SmartOne System session from CPF IT TH. 

       

 



2.2.1.3 FARM BUSINESS

No Project Name Type of IT Service Status % Remark Quarter
1 2 3 4

 1.

SMARTSoft_Farm : Change format of invoices, debit memos, credit memos in every program.


Improve printing format invoice, transfer slip, debit note/credit note to blank paper.


Objective : To decrease expenses for pre-print form

Business: Agro - Farm

Type of IT Services: Application Integration, Implementation, and Support

Priority: Low

CPF IT TH: Remote


26 May 23
-
Wait for Infra team to settle error to send finalize version to user
12 May 23
-Follow up date to go live
14 April 23
-Currently in PRD phase




       
 2.

APP SMARTSoft_Farm & SMARTSoft_Feed - Auto Generate PO Farm to FEED

Auto-generate sales order in Winfeed after getting PO feed from Winfarm and GRN auto generated in Winfarm after receive feed

Objective : Auto generate sales order in Winfeed after getting PO feed from Winfarm, and GRN auto generated in Winfarm after receive feed

Investment : NA


Business:
 Agro - Farm

Type of IT Services: Application Integration, Implementation, and Support

Priority: Med

CPF IT TH:

  Ser No. :26245 (CC2020006057)

17 Feb 2023
-Waiting for feed and farm from TH team to check web service issue data from farm not interface to feed and vice versa.
21 Dec 22
-New request for allocate freight charge(the transporter charger) for each product code.

-Currently Mr.danai amend the program regarding new requirement.
22 Nov 22
-Still waiting update from Mr Danai to fix freight charge not appear in GRN
       
3. 

iFarm_Sales System for Broiler Contract & Own Farm

Objective : To check sale credit limit via online. To capture accurate weight to flow to the system. To reduce manual work and able to generate DO automatically

Investment : RM225000.00

 

Business: Agro - Farm

Type of IT Services: Application Integration, Implementation, and Support

Priority: 

CPF IT TH:

 

Ser No. :32705 (CC2018130446)

23 Feb 23
- System capture the weight.
- TH will translate language to ENG
21 Dec 22
- TH retest again the weigh scale blueotooth with android mobile
- TH will fix program to capture the weigh.
15 Dec 22
- Retest again the weigh scale with the system on 15 Dec 22

       
4.  APP Shrimp Weighing System

Sale and Transfer Out module

Objective : Auto generate weight details report in system and auto send weigh details to system for create invoice 

Investment : RM 90 000

Business: Aqua - Farm

Type of IT Services: Application Integration, Implementation, and Support

Priority: Med

CPF IT TH: On Site

 

(CC2019131022) - 2019

26 May 23
Still testing the program
12 May 23
Test program for new requirement
13 Apr 23
- Add new file to separate for Johor Farm 1 and Johor Farm 2.
29 Mar 23
-
TH settle remaining issue for soft grade.

       
5.  SMARTSoft_Farm (AQUA) : Change format of invoices, debit memos, credit memos in every program.

Improve printing format invoice, transfer slip, debit note/credit note to blank paper.

Objective : To decrease expenses for pre-print form

Business: Aqua - Farm

Type of IT Services: Application Integration, Implementation, and Support

Priority: Low

CPF IT TH: Remote


26 May 23
-  
Amend for 3rd phase and will ask user again
12 May 23
-
Amended for 2nd phase and ask user feedback again
13 Apr 23
- Waiting for user feedback.
17 Mac 23
- Try to adjust based on Avian's invoice and delivery order.
       
6. 

APP Swine Farm - BPO PROJECT

Objective :  Propose to check all the document submitted for SO, invoice and GRN.

Investment : NA

Business: Swine - Farm

Type of IT Services: Application Integration, Implementation, and Support

Priority: Med

CPF IT TH: 

 

27 Mar 23
- TH is checking the table that has been created 
26 Jan 23
- Table view done created, user already acknowledge
09 Jan 23
- Checked some table that need to be added and confirming with Mr Wak again

       
7.  SMARTSoft_Farm (SWINE): Change format of invoices, debit memos,credit memos in every program. 

Improve printing format invoice, transfer slip, debit note/credit note to blank paper.

Objective : To decrease expenses for pre-print form

Business: Swine - Farm

Type of IT Services: Application Integration, Implementation, and Support

Priority: Low

CPF IT TH: Remote

 

21 May 23
-Waiting for user feedback
18 April 23
-Currently in edit process for Invoice .
27 March 23
-User checking the correct format.


       
8. 

APP Swine Farm - Power BI

Objective : 
Propose to see All Swine Business Report - Transaction Report, Efficiency Report, Performance Report by weekly, month and year.

Investment : N/A

Business: Swine - Farm

Type of IT Services: Application Integration, Implementation, and Support

Priority: Med

CPF IT TH: 

 

14 Apr 23
-Preparing all forms to submit to user sign
20 Feb 23
-Power BI go live
21 Dec 22
-TH show the functionality of the program.
-Power BI team amend the wording as per request from user .

       
9. 

Farm One - 1 Pilot Site 

To improve farm process with real time data.

Objective :
Mobile application for feeding chicken and online process via Mobile or Tablet such as receive chick ,receive feed ,dead and culling,feed inventory,breeder weight.

Investment : N/A

 

Business: Agro - Farm

Type of IT Services: Application Integration, Implementation, and Support

Priority: 

CPF IT TH: 



  21 Dec 22
- Implement one side on first quater on next year
22 Nov 22
- Re-test the program and appt with user soon
09 Nov 22
- UAT interface feed
       
10. 

APP Power BI 
-
Hatchery

Objective : Propose to see All Aqua Hatchery Business Report - Transaction Report, Efficiency Report, Performance Report by weekly, month and year.

Investment :N/A

 

Business: Aqua - Farm

Type of IT Services: Application Integration, Implementation, and Support

Priority: 

CPF IT TH: 

28 Jul 22
- Project continue 2023.
07 Feb 22
- Will start at Q3 September 22
24 Jan 22
- Will start at Q2
       
 11.

APP Customer Satisfaction Survey System
Hatchery Business

Objective : To get customer feedback to hatchery immediately through online. To analyze customer feedback data easily from app. To ease customer submit feedback via phone. To notify hatchery once customer submit feedback

Investment : NA

Business: Aqua : Farm

Type of IT Services: Application Integration, Implementation, and Support

Priority: Med

CPF IT TH:

  22 Mar 22
- Waiting TH update.
07 Feb 22 

- Waiting update from TH. TH still prepare for UA & UI.
22 Nov 21
- Project still under development. Mr Pornlerd got new team to develop this project.
       
 12. Ordering 3 week plan - Hatchery

Objective : To planning module for ordering shrimp

Investment : 

Business: Aqua - Farm

Type of IT Services: CPF IT - TH

Priority:

CPF IT TH:

   24 Jan 22
- Will start at Q4
       

 



2.2.1.4 FOOD BUSINESS

No Project Name Type of IT Service Status % Remark Quarter
1 2 3 4
 1.

APP OMS System
Upgrade OMS Swine / Chicken

Objective : To upgrade OMS system for Swine and PKA

Investment : USD 7,283.00

Business: Agro & Swine - Food

Type of IT Services: Application Integration, Implementation, and Support

Priority:

CPF IT TH: 

  26 May 23
- Already follow up with Mr New
17 April 23
- Mr New inform he will continue meeting with users after project cutting plan swine is completed.
29 Mar 23
- Waiting Mr New Confirmation for meeting discussion again with users

       
2.

APP SMARTSoft Win Processing

Objective :  Check business rules and policies by the system to make it accurate. Reduce paper and work time. Self-service application for the employee. Data analysis for decision making.

Investment : 

 Business: Aqua - Food

Type of IT Services: CPF IT - TH

Priority: 

CPF IT TH:

  25 May 23
- Discussion with Mr Chalermsak on 09 May, expected timeline to be followed. Blue print to be confirmed on July
23 Mar 23
- Mr/Ms Veerapat already acknowledge and now in planning to start the project
15 Mar 23
- Sent CR 230025570 and email to TH
       
3. 

APP Axons POS System for Star Coffee

Objective :  New pos system to implement for Star Coffee Project 

Investment : 

Business: Food

Type of IT Services: CPF IT - TH

Priority: 

CPF IT TH:

  25 May 23
- Waiting user to revert back the form, already remind user to sign
13 Apr 23
- Already email to user the project completion form, waiting user to revert back
27 Mar 23
- Walkthrough report in imaster with user and support user for any issues, will close this project by 06 April 23

       
 4.

APP Power BI for AXONS POS System for Star Coffee

Objective :  To shows in graphic data for the sales dashboard of Star Coffee

Investment : 

Business: Food

Type of IT Services: CPF IT - TH

Priority: 

CPF IT TH:

  25 May 23
- Remind user again to check and to give feedback
13 Apr 23
- Asked and waiting user to feedback any issue 
27 Mar 23
- Power BI TH team complete for go live, already give email list for access to TH
       
 5.

APP SMARTSoft_Food Cutting Plant

 

Objective : Separate slaughter and cutting plant
Investment : 

Business: Swine - Food

Type of IT Services: Application Integration, Implementation, and Support

Priority:

CPF IT TH: 

  10 May 23
- Still monitor issues because not stable yet when close period
13 Apr 23
- Still waiting TH team to solve the issues listed in issue log
28 Mar 23

- Keep track of issue log in Line group and waiting TH to check

       
 6.

APP Axons POS System for Star Coffee - QR Ordering

Objective :  QR Ordering for online order

Investment : 

Business: Food

Type of IT Services: CPF IT - TH

Priority: 

CPF IT TH:

   10 May 23
- Meeting with vendors for their new enhancement for QR ordering
26 Apr 23
- Meeting with TH for O2O to introduce them for QR ordering

       
6. 

APP SMARTSoft_Food Slaughter Plant

Production Costing

Objective : 
Investment : 

Business: Agro - Food

Type of IT Services: Application Integration, Implementation, and Support

Priority:

CPF IT TH: 

  23 Feb 22
- Waiting TH Side
22 Nov 22

- We appt with user on Dec
07 Nov 22

- Review Slaughter Processing
       
 7.

APP SMARTSoft_iQC
Paperless Checklist

Objective : To use system checklist in SMARTiQC and reduce using paper for each warehouse

Investment : NA

Business: Agro - Food

Type of IT

Priority: High

CPF IT TH:

  (CC2021006132) - 2020

23 Feb 2023
Waiting thailand team for the quotation and waiting  user decision to use Thailand team or vendor implementation
25 April 2022
- User Senawang Plant already done demo 474 Form to TH Food team.

- Waiting Quotation details From TH Food Team.
5 April 2022
- User Senawang  will demo 474 Form TH Food team.

       
8.
APP SMARTSoft_Food QR Code

Objective : To implement QR Code for F2F project (EQ Processing Malaysia)

Investment : NA


Business:
 Agro - Food

Type of IT Services: Application Integration, Implementation, and Support

Priority:

CPF IT TH:

  (CC2020087676) - 2020

23 Feb 22
- Waiting TH Side
30 May 22
- Waiting TH update.
24 Jan 22
- Waiting TH update

       

9.

APP SMARTSoft_iDC Further Processing and Slaughter Plant
Distribution Center (Barcode Warehouse Management) new version

Objective : for Warehouse and Equipment Management

Investment : NA


Business:
 Agro - Food

Type of IT Services: CPF IT - TH

Priority: High

CPF IT TH: On Site

 

(CC2020148253) - 2020

24 Jan 22
- Will start at Q4

28 May 21
- Will proceed at quarter 4
26 Apr 21

- Implement after APP SMARTSoft_Food QR code for slaughter Poultry

       

10.

APP SMARTSoft_Food QR Code
Implement warehouse management system for Further Plant

Objective : 
Investment : RM150000.00 (Senawang)


Business:
 Agro - Food

Type of IT Services: CPF IT - TH

Priority: High

CPF IT TH: On Site

 
23 Feb 22
- Waiting TH Side
24 Jan 22
- Will start at Q4
       

11.

APP SMARTiPOS Membership Point

Objective : XXXX

Investment : NA

Business: Swine: Food

Type of IT Services: Application Integration, Implementation, and Support

Priority:

CPF IT TH:

23 Feb 22
- Waiting TH Side
24 Jan 22
- Waiting Ms P do the implementation

28 Jan 21
- Waiting CR from the user

       

 


2.2.1.5 PET

No Project Name Type of IT Service Status % Remark Quarter
1 2 3 4
1

PCM Ecommerce

Objective : Change iSale to Mobile Application and B2B eCommerce platform.

Investment : NA


Business: PCM

Type of IT Services: CPF IT - TH

Priority: Med

CPF IT TH:

 
CR: :CC2021119542

17 April 23
- Ongoing monitor and support by thailand side
10 Jan 23
- Phase 3 UAT Ecommerce, user will give feedback on 27th Jan 23 
20 Dec 22
- Still in testing phase
       

2.

APP Maajoy Application
Payment Method

Objective : 
Investment : 

Business: PCM

Type of IT Services: CPF IT - TH

Priority:

CPF IT TH:

 

23 Feb 22
- Waiting TH Side
09 May 22
- After go live B2B ECOMMERCE  project. 
24 Jan 22
- We will start after PCM eCommerce.

       

2.2.2 WAITING FOR CPF PH

No Project Name Type of IT Service Status % Remark Quarter
1 2 3 4

1.

APP POND ID (Synergy with CPF IT Philipines)

For Sales Team & Farm record pond information

Objective : To improve windows version and emhance the performance of server with application including the security.

Investment : NA

Business: Aqua - Farm

Type of IT Services: CPF IT - PH

Priority: High

CPF IT TH:

 

23 Mar 22
- Meeting with IT Philiphine. Introduction to POND ID system to MY team.
24 Jan 22

Philiphine finish implementation already. Waiting PMO for Malaysia.
17 Nov 22
- Pond ID Presentation by CPF PH.

       

 

2.3 WAITING CR FROM USER

3. PROJECT 2024

4. PROJECT CANCEL/HOLD

No Project Name Type of IT Service Status % Remark Quarter
1 2 3 4
1.

INF Telephone System IP PABX
Replace PRI PABX due to service termination & obselete by telco
Objective : To setup and implement IP PABX for SFM-Beranang, PKA-Tg.Langsat and PKA-PortKlang
Investment : 

IO No. : 3000711 (RM50,000)

Business: ALL
Type of IT Services: Application Integration, Implementation, and Support
Priority: Med
CPF IT TH:

13 Oct 22
-Project cancel


PKA Port Klang
Current Model :Toshiba Strata CIX670

104 -single line , 16 Digital Line

 

       
2.

INF Tech Refresh POS Machine (Windows Embeded 7) & SC (Windows 7)
21 Outlets
Objective :  To refresh old POS machine and improve windows version in order to maximize system performance 
Investment : 

Business: Swine
Type of IT Services: CPF IT - BI
Priority: Med
CPF IT TH:

13 October 22
- On hold 

11 Aug 22
-Sourcing for a cheaper alternative solution

23 Mar 22
- Will start purhase in July 22
21 Feb 22

- Finish setup POS machine using CLL Brand

       

3.

INF & SOFTWARE Upgrade Time Management System Agro
Upgrade hardware (fingerprint / face recognition) and link to Sage EasyTime
Objective : 
Investment : 

IO No. : xxxx (RM xxxx) 

Business: Agro

Type of IT Services: Application Integration, Implementation, and Support


Priority: Med


CPF IT TH:

13 Oct 22
-
Project cancel
11 Aug 22
-
Waiting for vendor delivery 
04 Jul 22
- Start implement at PKA-Senawang site (5 unit)

       

4.

APP B2B Ecommerce

Objective : Selling products to business customer & individual. Customer can buy the products through e commerce platform. Convert cash customer from MT & FS to e-commerce. CPO). Business to Business (B2B)

Investment : NA

Business: Agro - Food

Type of IT Services: Application Integration, Implementation, and Support

Priority: High

CPF IT TH: On Site

 
(CC2020127877) - 2020

09 May 22
- Stop the project implementation because user no respond regarding the project implementation

07 Feb 22
- Web service and API already completed.
24 Jan 22
- Waiting user to Published Phase 1

       

5.

eCommerca Phase 2 : Interface to SMARTSoft

Objective : Selling products to business customer & individual. Customer can buy the products through e commerce platform. Convert cash customer from MT & FS to e-commerce. CPO). Business to Business (B2B)

Investment : NA

Business: Agro - Food

Type of IT Services: Application Integration, Implementation, and Support

Priority: High

CPF IT TH: On Site

   (CC2020127877) - 2020

09 May 22
- Stop the project implementation because user no respond regarding the project implementation

07 Feb 22
- Web service and API already completed.
24 Jan 22
- Waiting user to Published Phase 1

       
6.

DEV eCommerce Phase 1
Objective : To implement Ecommerce site to sell CP Food Product Online
Investment : RM3,800

Business: Agro

Type of IT Services: Infra Cloud, Application Integration, Implementation, and Support

Priority : High

CPF IT TH:

13  Oct 22
- Stock issue 
21 Feb 22
- Waiting for go live date from Project Owner

29 Nov 21
Waiting for go live date and pending due to insufficient stock

1 Nov 21
- Waiting User to confirm date to go live

       
7.

 

APP B2B eCommerce

Objective : 
Investment : 

Business: Swine - Food

Type of IT Services: Application Integration, Implementation, and Support

Priority: 

CPF IT TH:

 

09 May 22
- Will start after PCM Ecommerce completed

       
8.

APP SMARTSoft ImportiSolution

Objective : 
Investment : 

 Business: Agro

Type of IT Services: Application Integration, Implementation, and Support

Priority: High

CPF IT TH:

  2020

7 Feb 22
-Review Program New version for overseas

24 Jan 22
- Change to interface exchange rate with bank into sap system

26 Apr 21
Waiting for user confirmation.
       

 